Tuesday, October 15, 2019

We were both at the house early Tuesday morning for a marathon session with successive contractors. Things are happening quickly now, although the schedule is now that the house will not be ready until the end of November.

Both of the driveways are now disrupted with trenches. Picture 1 shows the trench in the lower part of the west driveway. This is for a new waterline, which we will connect to a new, larger water meter. Picture 2 shows the branch of this trench that runs to the garage/apartment. Picture 3 shows the trench running up the hill to the house.

Picture 1 – Trench for the new waterline in the lower section of the west driveway.
Picture 2 – Branch in the water line trench to service the garage/apartment.
Picture 3 – The trench continues up to the house. Notice, on the upper right, the start of the framing for the stairs from the garage to the apartment and the deck.

In the upper right of Picture 3, you can see a large piece of wood. This is the stringer for the top of the stairs that will run from the deck, back down to the apartment and then the garage. These are the forms that will allow them to pour the cement stairs. Picture 4, shows this construction from the top.

Picture 4 – Top of the stairs running to the apartment and then the garage.

Picture 5 shows trenching on the east side of the house, for electrical conduits. The conduit running along the house will go down to the garage/apartment. The conduit running away from the house is for the main power connection to the utility pole. Picture 6, shows the continuation of the trench for the main power. At the far end is a utility pole hiding in the trees.

Picture 5 – Electrical conduits on the east side of the house. The conduit running along the house will go down to the garage/apartment. The conduit running away from the house is for the main power connection to the utility pole.
Picture 6 – Continuation of the trench for the main power. This runs down the east driveway to the utility pole that is hiding behind the tree at the bottom end of the trench.

Picture 7 shows the roofers getting ready to apply the primer for a cement-based coating that will be decking for the deck on the east side of the house.

Picture 7 – Workers preparing to apply the final coating to the deck on the east side of the house.