All the rebar is up. The work passed two inspections this morning. Originally, we were told that they would pour cement starting at 7 tomorrow, then it was noon, and finally it is now 2 PM. The problem is that, although all the rebar and most of the forms are in place, the forms in the last few sections have been particularly difficult.
Pictures 1 and 2 shows some of the finished forms; Picture 2 shows what will eventually be the view out of one of the windows.
However, Pictures 3, 4, and 5 show the guys working on one section of forms, around what will be the entrance doors, that proved particularly difficult to get into place and straight up and down. Another factor slowing work down is that one of the four workers developed a bad case of sciatica in the morning and could not work. With all of these things they will need the morning to get everything finished to be ready to pour concrete.