Today was disappointing. Somebody forgot to order a forklift and so the materials to be used to create the structure for the garage ceiling had to be ferried by small truck from the street to the garage and it took two hours. Then it turned out that the truck had only brought 10 props, which are a little gizmo that sits on top of the posts that support the ceiling. So they could only put up 10 posts. They also put up wooden headers and then organized all the materials.
You can see 8 of the posts here where they have covered the rectangular part of the back of the garage. The remaining triangle will be done with one rectangle through its middle, and then 2 small triangles. More props will be delivered tomorrow. At the top of the posts is a plastic rack on which the plywood will be laid followed by some spacers on top of that and then the concrete.