Monthly Archives: June 2019

June 25, 2019

Progress again — a quick update. Picture 1 shows the continuing work attaching the insulation panels to the outside of the apartment. Probably no work tomorrow because the electric company will be turning off the electricity and closing part of Modjeska Canyon Road to replace some poles. Pictures 2 and 3 show the newest development: […]

Posted in house | Leave a comment

June 21, 2019

It has been almost two calendar weeks (and fully two work weeks) since the last post. For much of this time, not much was happening. Then, this week there was a problem on the WordPress site that Nina uses to host the blog and we could not log in to create a new entry. But […]

Posted in house | Leave a comment

June 9, 2019

Last week the process of installing the windows got close to completion. The plan is to do the last steps Monday, and then on Tuesday the house will be ready both to install the drywall inside and the insulation and stucco outside. The largest of the windows is the combination of fixed windows and sliding […]

Posted in house | Leave a comment

Sunday, June 2, 2019

On Saturday, our friends from New Jersey Chris and Claudia Van Wyk arrived to spend the day. We took them to the Farmers ‘ Market in Irvine, and then after lunch we drove out to Modjeska. Unlike many recent Saturdays, there were no workmen other than Pete. He had planned to go to his dentist […]

Posted in house | Leave a comment